PROJECT COSTS |
---|---|---|---|---|---|
Alaska | KB Subdivision Water Service Association, City of Soldotna | 170 | Treatment | Arsenic | $764,000 |
Arkansas | State-wide | Varies | Consolidation studies | Multiple health-based violations | $480,000 |
Colorado | Town of Cheraw | 256 | Treatment | Radium | $376,267 |
Colorado | Town of De Beque | 89 | Treatment | Total Trihalomethanes | $191,013 |
Kansas | City of Clayton | 54 | Source | Arsenic | $520,000 |
Louisiana | Village of Saline | 265 | Consolidation studies | Total Trihalomethanes, haloacetic acids | $816,850 |
Missouri | City of Chamois | 377 | Source | Treatment technique | $678,478 |
Montana | Cluster County – Palisades Apartments; Kalispell – Morning Star | Varies | Treatment, Transmision/ Distribution | Treatment technique, extension of service | $414,000 |
Nebraska | Martinsburg (Phase 2) | 89 | Blending Well: above ground work | Uranium, nitrate (MCL) | $370,000 |
Nebraska | Martinsburg (Phase 3) | 89 | Storage | Uranium, nitrate (MCL) | $570,780 |
New Jersey | North Shore Water Association | 105 | Treatment | PFOS | $495,000 |
New Mexico | State-wide | Varies | Technical, Managerial and Financial Assistance | Multiple health-based violations | $512,647 |
New York | Town of Ticonderoga | 262 | Treatment, Source | Surface water treatment, crysptosodium | $1,325,000 |
North Dakota | Tri-County Water District | Varies | Transmission/ Distribution | Additional service | $280,000 |
Ohio | Garrett Ridge | 174 | Transmission/ Distribution | Extension of Service | $799,000 |
Oregon | Swisshome Village | 24 | Source | Disinfection Byproducts, new source | $110,000 |
Oregon | London Water Co-op | 63 | Treatment | Turbidity, filtration | $221,000 |
Oregon | City of Adrian | 180 | Technical, Managerial and Financial Assistance | Arsenic , Capacity development/treatment | $20,000 |
Oregon | Garden Valley Water Association | 84 | Treatment | Turbidity, new filtration plant | $183,000 |
Oklahoma | Towns of Loyal and Brooksville | Varies | Treatment/ Consolidation | Multiple health-based violations | $671,000 |
South Dakota | Town of Hermosa | Varies | Transmission/ Distribution; Technical, Managerial and Financial | Capacity development, Extension of Service | $336,000 |
Washington | Ferry County | County-wide | Technical Assistance, Consolidation | Compliance issues | $65,000 |
Washington | Duck Lake Water Association and Johnson Creek Water Systems | 48 | Consolidation | Uranium, Arsenic | $692,894 |